Gail has picked colour for her feature wall. Striking cyan!
Flooring laid in front bedroom, click vynil colour blonde oak.
Tuesday, 1 December 2015
First coat of paint!
Wednesday, 25 November 2015
All plastered. Back boxes for socket outlets are in and cables drawn through . Garage ceiling has first layer of boarding now filled and taped ready for next layer.
Sunday, 22 November 2015
Internal partitions are up,
on the advice of the plasterer the old brick wall of the house has been sheeted with plasterboard on plaster dabs. now whole upstairs is plastered and well into process of drying out.
Even fitted a door!
Saturday, 14 November 2015
Insulated plasterboard all now up on walls . Still got round the widows to do. Now started on internal partitions and doors.