Tuesday, 27 November 2018

Kitchen and dining room now temporarily in garage! 

All clear to lift floors 


Wednesday, 14 November 2018



The steel is up!!!
There are railway bridges made of lighter section than this!!


Here it is now encased in 2 cubic metres of reinforced concrete! 

Thursday, 18 October 2018

Tiles and ply removed from kitchen floor in readiness for props under bathroom floor.

New doorway created where kitchen window used to be.


Quite a few bricks removed.





Monday, 15 October 2018

Steel deliverer sat morn. It now rests near where it will be installed.  The props can now go in and the back wall come down.
The props are in place in former dinning room. However kitchen floor and ceiling need part removed to prop under bath room.




Wednesday, 10 October 2018

French doors no more!

Back door no more!

Steel coming on Saturday! 

Friday, 5 October 2018


Exterior  cladding complete, including spotlights fitted!