Wednesday, 10 October 2018

French doors no more!

Back door no more!

Steel coming on Saturday! 

Friday, 5 October 2018


Exterior  cladding complete, including spotlights fitted!

Tuesday, 24 July 2018

Cederal up to window cill height.

Building inspectors from next door!

Saturday, 14 July 2018

Cederal cladding well underway. Waiting for winfow cills befor cladding all the way up




Tuesday, 8 May 2018

New drainage arragement. Hope this satisfied building control!



Saturday, 5 May 2018

Well, the man from building control didn't like my dtainage arrangement!
The problem is the down portion goes into tbe old drain with a 90 degree T.
He is worried about solids going the wrong way in the pipe so need to replace the 90 t with a 45, so big hole is now dug!