And have to be carried manually through garage to back of house
Then fitted!
All installed except for triangle window which is unforunately wrong size!
Tuesday, 10 October 2017
The begining of an outside wall! This is where the back door goes.
Type1 laid and compacted by lunch time!
Friday, 29 September 2017
15 tonnes of type1 ordered for sat morn, arrived 1 day early!!
Friday, 22 September 2017
Progress to date, diagonal brace for steel work, granite plinth to take sliding doors. Timber round all windows.
Tonight was shutter work for plinth for back door but run out of light!