Friday, 12 January 2018

This is what 2 grand of insulation looks like!


Garage 

Tuesday, 21 November 2017

Doors and widows arrive manually us trial!







And have to be carried manually through garage to back of house

Then fitted!

All installed except for triangle window which is unforunately wrong size!




Tuesday, 10 October 2017

The begining of an outside wall! This is where the back door goes.






Type1 laid and compacted by lunch time!

Friday, 29 September 2017

15 tonnes of type1 ordered for sat morn, arrived 1 day early!!

Friday, 22 September 2017

Progress to date, diagonal brace for steel work, granite plinth to take sliding doors. Timber round all windows.
Tonight was shutter work for plinth for back door but run out of light!


Also, now have garage door!