Wednesday 30 July 2014

Another couple of courses of bricks up today. Scaffolding also moved up a stage. Three courses to go before garage door lintel.

Tuesday 22 July 2014

Only mad dogs and englishmen go out in the mid day sun!
un usual to have to rig sun shade rather than water cover!

Thursday 17 July 2014

Scaffolding now on site and up as bricks are high enough to be out of reach from the ground. Now cracking on laying more bricks.

Sunday 6 July 2014

Now 12 courses of bricks above damp proof level. Couple of questions have arisen re the insulation and the acceptable cavity gap. Hope to have this resolved soon so I can order the insulaion.