Tiles and ply removed from kitchen floor in readiness for props under bathroom floor.
New doorway created where kitchen window used to be.
Quite a few bricks removed.
Monday, 15 October 2018
Steel deliverer sat morn. It now rests near where it will be installed. The props can now go in and the back wall come down.
The props are in place in former dinning room. However kitchen floor and ceiling need part removed to prop under bath room.
Wednesday, 10 October 2018
French doors no more!
Back door no more!
Steel coming on Saturday!
Friday, 5 October 2018
Exterior cladding complete, including spotlights fitted!