Roof now complete! Almost! One ridge clip broke on fitting but apart from that ridge and verges in place. Gutters next!
Monday, 28 September 2015
Saturday, 26 September 2015
In an attemp to make the valley gutters 100% dry fit instead of mortaring the tiles on, have wraped the batton ends in dpm.
Also both side now tiled. Photo only shows rear aspect due to finishing fromt in no light!
Just hsve front valley and both verges to trim also ridge and verges to fit, then roof is complete!
Also both side now tiled. Photo only shows rear aspect due to finishing fromt in no light!
Just hsve front valley and both verges to trim also ridge and verges to fit, then roof is complete!
Wednesday, 23 September 2015
Wednesday, 16 September 2015
Roof covered with marley breathable membrane. There are 600mm strips of same under valley gutters, the membrane from the old and new roofs is overlapped the under valleys membrane as specified by the gutter manufacturers.
The front aspect of the new roof is counterbattoned and battoned ready to tile!
The front aspect of the new roof is counterbattoned and battoned ready to tile!
Monday, 14 September 2015